How much gravel do I need?

Work in cubic yards: length (ft) × width (ft) × depth (ft) ÷ 27. Convert depth from inches to feet first (4 in = 0.33 ft). Then multiply cubic yards by about 1.4 to estimate tons (gravel runs ~1.4 tons/yd³), and add ~10% for compaction and waste. Example: a 10 × 10 ft pad, 4 in deep = 100 × 0.33 ÷ 27 ≈ 1.2 yd³ ≈ 1.7 tons, ~1.9 with compaction.

Source: yd³ = L×W×D(ft) ÷ 27; tons ≈ yd³ × 1.4 ·

length width depth L×W×D (ft) ÷ 27 = yd³ yd³ × 1.4 ≈ tons
Gravel by the yard: length × width × depth in feet ÷ 27 = cubic yards; multiply by ~1.4 for tons, and add ~10% for compaction. An estimating method, not a code requirement.

Gravel is sold by the cubic yard or by the ton, so an estimate is a volume calculation with a weight conversion on the end.

The method

  1. Measure the area and depth. Length and width in feet; depth usually in inches → convert to feet by dividing by 12 (4 in = 0.33 ft, 6 in = 0.5 ft).
  2. Volume in cubic yards: L(ft) × W(ft) × D(ft) ÷ 27 (there are 27 cubic feet in a cubic yard).
  3. Convert to tons (if buying by weight): multiply cubic yards by about 1.4 — most crushed stone and gravel weighs roughly 1.4 tons per cubic yard (≈ 2,800 lb). Sand and some bases differ, so check your supplier’s density.
  4. Add ~10% for compaction and spillage — a compacted base settles, so you place more loose material than the finished volume.

Worked example

A 10 ft × 10 ft gravel pad, 4 inches deep:

  • Volume: 10 × 10 × 0.33 ÷ 27 ≈ 1.2 cubic yards.
  • Tons: 1.2 × 1.4 ≈ 1.7 tons.
  • With ~10% compaction: order ≈ 1.9 tons (or ~1.3 yd³).

Watch for

  • Depth is the big lever. Doubling depth doubles the gravel — a 2-inch overcut across a big area adds up fast.
  • Density varies. Pea gravel, ¾” crushed, and road base aren’t identical weights; the 1.4 tons/yd³ figure is a planning average.
  • Round up to the delivery minimum. Bulk gravel ships by the full or half-yard/ton — buy a little over, not under.

Count it automatically with the excavation / aggregate calculator. This is an estimating method, not a code requirement.