Is my project new construction, an alteration, or a repair?

New buildings follow the IBC or IRC in full. Work on an existing building follows the IEBC, which sorts it into repair, alteration (Levels 1–3 by how much you change), addition, change of occupancy, or relocation. The bigger the work, the closer it must come to new-construction rules — your category sets how much of today's code applies.

Source: 2021 IEBC §301 & Chs. 4–11 (classification of work) ·

These are model codes — the edition your jurisdiction has adopted, plus any local amendments, is what governs. Confirm with your AHJ.

the bigger the job, the more of today's code applies new construction = full code Repair Alteration Addition Change of use alteration splits into L1 · L2 · L3 (L3 = work area over 50%)
New buildings follow the IBC/IRC in full; work on an existing building follows the IEBC, which scales the rules to the work — repair, alteration (L1–3), addition, or change of occupancy (2021 IEBC §301).

Why it matters: you rarely have to bring an entire existing building up to today’s code just to touch part of it. The International Existing Building Code (IEBC) scales the requirements to the kind and size of work — so naming the work correctly tells you how much of the current code applies.

The categories, roughly from least to most involved:

  • Repair — fixing or replacing damaged parts to a safe condition (patching, swapping a broken component). The lightest requirements.
  • Alteration — any change to an existing building that isn’t a repair, addition, or change of occupancy. The IEBC splits these into Level 1 (replace/cover like-for-like, no space reconfiguration), Level 2 (reconfiguring space, new walls/doors/systems), and Level 3 (work area over 50% of the building — closest to new-construction rules).
  • Addition — increasing floor area, height, or number of stories. The new part is generally treated like new construction.
  • Change of occupancy — using the building for a new purpose that changes its occupancy classification; can trigger broader upgrades.

The IEBC also offers three compliance paths (prescriptive, work-area, and performance) that can’t be mixed on one project. Because classification and the path chosen drive real cost, confirm the work type and approach with your AHJ and the adopted edition.